Report on activities in the Group -1 project for the week ending 2024-09-12.

[WE6.2.1] Publish pre-train single version containers

[edit]

If we publish a versioned build of MediaWiki, extensions, skins, and Wikimedia configuration at least once per day we will uncover new constraints and establish a baseline of wallclock time needed to perform a build.

Progress update
  • Stage: Engineering/Development
  • Dan made some minor improvements to the jenkins-deploy and release scripts in preparation for defining a job to rsync patches, scap prep/sync.
  • Dan is thinking about refactoring the jenkins-deploy and release scripts to consolidate scripts only used by Jenkins jobs into jenkins-deploy. This can be done after getting things to work initially.
Any new metrics related to the hypothesis
  • None
Any emerging blockers or risks
  • None
Any unresolved dependencies - do you depend on another team that hasn’t already given you what you need? Are you on the hook to give another team something you aren’t able to give right now?
  • Not yet
Have there been any new lessons from the hypothesis?
  • No
Have there been any changes to the hypothesis scope or timeline?
  • No